Good News, Gregorio Del Pilar (PS-15) BRP Repair reaches 70 Percent Readiness and Ready For Trial

Zikrul
By -
0
Good News, Gregorio Del Pilar (PS-15) BRP Repair reaches 70 Percent Readiness and Ready For Trial

Completion of brp gregorio del pilar repairs seen this december. Manila the repairs of the offshore patrol Vessel BRP Gregorio Del PilerPS-5 are estimated to be completed by the end of december.

The ship's repair is already 70 complete with an estimated completion date around the last week of december 202, said philippine navy PN spokesperson commander Benjo Nagranza in a message to the philippine news agency when sought for updates on the naval vessel wednesday night.

Dock and sea trials for BRP Gregorio Del Pilerr were conducted in the last week of november. another sea trial will be scheduled upon correction of noted deficiencies if any found on the previous sea trial, Negranza said.

Despite the brp gregorio del pilar undergoing maintenance, he assured the public that the PN vigilantly stands guard at our borders effectively safeguarding philippine waters. One of the ship's two variable pitch propellers was damaged, along with its propeller hub after its grounding off Hasahasa shoal in august 2018.

Nagranza earlier said the dry docking and other related repairs of BRP Gregorio Del Pilar are expected to be completed by september. Difficulties in procuring parts in the ongoing coronavirus disease 2019 Covid-19 pandemic have moved the completion of the repairs of the BRP Gregorio Del Piler to the latter part of 2021.


Subscribe Daily Post or Follow Google News to update information quickly or visit this Link: https://news.google.com/publications/CAAqBwgKML-1rAswzMDEAw
Tags:

Post a Comment

0Comments

Post a Comment (0)

#buttons=(Ok, Go it!) #days=(20)

Our website uses cookies to enhance your experience. Learn more
Ok, Go it!